Meter Alteration

 

VIC Electricity

Powercor/United/Citipower

This is raised directly to the distributor via their network portal. Please see below:

Jemena/Ausnet

  • You must have a valid Sumo account.
  • Engage with an electrician, they will confirm what work is required.
  • They will then need to complete and send an EWR (Electrical Works Request) form and any other required documents to connections@sumo.com.au
  • Please allow at least 20 business days for this request to complete.

 

VIC Gas

  • You must have a valid Sumo account.
  • Please fill out the alteration form (You may need a plumber to help you fill this out) and email to connections@sumo.com.au
  • Please allow at least 20 business days for this request to complete.

 

NSW Electricity

  • You should engage an Accredited Service Provider (ASP), this is a type of electrician.
  • Your electrician will need to complete any works required and notify your distributor.
  • If any action is required by Sumo, your electrician will need to notify Sumo via an email to connections@sumo.com.au

 

NSW Gas

 

QLD

  • You must have an active Sumo account.
  • Engage with an electrician, they will confirm what work is required.
  • Any alterations need to be requested to Energex directly, through their online portal.
  • Energex will send an EWR (Electrical Works Request) to Sumo and we will raise any service orders required.
  • Please allow at least 20 business days for this request to complete.

 

SA

  • You must have an active Sumo account.
  • Engage with an electrician, they will confirm what work is required.
  • Any alterations need to be requested by your electrician to SAPN directly, through their online portal.
  • Sumo will then be notified by SAPN, and we will raise any service orders required.
  • Please allow at least 20 business days for this request to complete.